Solution Regenerator Tower Project
Chemical Plant Beulah, ND
2013
Remove and Install Solution Regenerator Tower Project
ICI provided services to remove the existing tower from service in pieces and erect the new tower during the tight turnaround schedule in the spring of 2013. Services provided included removal and installation of piping, structural steel, equipment, and insulation with the final vessel lift tipping the scales at 327,000 pounds.